Incorporation Of One-Sided And Unreasonable Clauses In Apartment Buyer's Agreement Constitutes An Unfair Trade Practice: Supreme Court
In the case of Ireo Grace Real Tech Pvt. Ltd. vs. Abhishekh Khanna &
Others the appellant filed appeals to the National Consumer Disputes
Redressal Commission, which ordered a refund of the amounts deposited by
apartment buyers in the Corridors project developed in Sector 67-A,
Gurgaon, Haryana, due to the excessive delay in completing the construction and
obtaining the Occupation Certificate. The appeal was filed under section 23 of
the Consumer Protection Act by the appellant.
The case at hand talks about the scenario in which the license for construction
was granted to the developer by the Department of Town and Country Planning for
the development of a group housing colony on a large plot of land covering
approximately 37.5125 acres, with various towers containing 1356 flats. The main
crux of the case is about handing over the possession of the property.
The main reason which emerged in this case for the delay in possession was
issuance of the NOC by the fire authority. The commissioner of Municipal
corporation raised 16 objections regarding the proposed firefighting scheme
(Letter dated 30.12.2013). The developer submitted on 22.01.2014 that the
Commissioner's objections had been remedied. Municipal Corporation (Letter dated
28.03.2014) informed the developer that the inadequacies in application for fire
NOC has not been rectified. The developer was granted 15 days™ time to rectify
the defects. Failing which, the application would be deemed to be rejected. In
the end on 27.11.2014, the director, Haryana Fire Service granted approval to
the developer for the same.
The purchasers filed complaints before the National Commission seeking
reimbursement of the instalments along with interest because, within the agreed
period of 42 months + 6 months (grace period) the plaintiff had failed to grant
possession. However, the purchase agreements prevented a buyer from terminating
until 12 months after the expiry of the 42 + 6 months period, and further
restricted compensation for delayed delivery to ₹7.5 per square foot per month
for a period of 12 months.
The developer said the National Commission did not have the power under the
Consumer Protection Act to nullify the terms of a contract alleged to be unfair
or one-sided. This is apparent by comparison with the provisions of the Consumer
Protection Act 2019, which give the consumer forums this particular power. The
National Commission disagreed and laid down in the purchase agreement that the
offending clauses were unilateral and unfair. In addition to this National
Commission also instructed the developer to repay the instalment it received
together with the interest of 10% per annum.
The supreme court mentioned the Section 2(1)(C) of the 1986 Act which says that
a complaint can be filed in respect of an unfair trade practice, and also
mentioned the Section 2(1)(r) which provides an inclusive definition of an
unfair trade practice. The Supreme Court held that the consumer for a are able
to declare contractual terms as unfair or one sided:
as an incident of the power to discontinue unfair or restrictive trade
practices. While the 2019 Act specifically defines an unfair contract
and says these can be declared null and void, this is only a statutory
recognition of a power which was implicit under the 1986 Act.
The Supreme Court stated that delays in delivery of ownership amounted to a
service deficiency which entitled the purchaser to a refund of the money paid
together with a decent compensation. In accordance with the agreement of Rs. 7.5
per square foot per month, the compensation for delayed possession amounts to
just 0.9% to 1% annual interest, which was clearly insufficient. In cases where
the customer was entitled to a reimbursement, the Supreme Court directed
interest payments to the buyer at 9% from the date of delivery to the actual
reimbursement date.
The position in accordance with the 1986 Act is effectively equivalent to the
2019 Act, and the decision may not be restricted only to claims against
developers. In addition this might require sellers and service providers, to
review practices of the use of standardized take it out or leave
contracts in their dealings with consumers by specifically including unfair
contract provisions and the power to set the same aside under the 2019 Act.
A similar case also exists On April 2, 2019, the Supreme Court passed a judgment
in the matter of Pioneer Urban Land & Infrastructure Limited v. Govindan Raghava,
wherein the Court held that the incorporation of one-sided clauses in an
Agreement constitutes the unfair trade practices within the meaning of Section
2(r) of the Consumer Protection Act, 1986, and such clauses cannot bind a party.
Law Article in India
You May Like
Please Drop Your Comments