The case of
Pragati Construction Consultants v. Union of India and Bharat
Broadband Network Limited v. Sterlite Technologies Limited, adjudicated by a
Full Bench of the Delhi High Court, addresses a critical procedural issue in the
context of applications filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (A&C Act). Specifically, the court was tasked with
determining whether the non-filing or defective filing of a Statement of Truth,
as mandated under Order VI Rule 15A of the Code of Civil Procedure, 1908 (CPC),
as amended by the Commercial Courts Act, 2015 (CC Act), renders an application
under Section 34 of the A&C Act "non-est" (non-existent in the eyes of law).
This issue is significant due to the strict limitation period prescribed under
Section 34(3) of the A&C Act, which allows only three months, extendable by an
additional thirty days with sufficient cause, for filing an application to set
aside an arbitral award.
Factual Background: The case arose from two separate matters referred to
the Full Bench of the Delhi High Court. In the first matter, OMP(COMM) 20/2024 (Bharat
Broadband Network Limited v. Sterlite Technologies Limited), the petitioner
filed an application under Section 34 of the A&C Act on October 27, 2023, to
challenge an arbitral award but failed to include a Statement of Truth as
required under Order VI Rule 15A of the CPC, applicable to commercial disputes
under the CC Act. This omission led to a dispute regarding the validity of the
initial filing.
In the second matter, FAO(OS)(COMM) 70/2024 (Pragati Construction Consultants v.
Union of India), the issue of non-filing of the arbitral award itself was
referred to the Full Bench, but the present case study focuses solely on the
issue of the Statement of Truth as raised in OMP(COMM) 20/2024. The core
contention was whether the absence or defect in the Statement of Truth rendered
the application non-est, thereby failing to stop the limitation period under
Section 34(3) of the A&C Act.
Procedural Background: The procedural journey of this case began with a
reference made by a learned Single Judge of the Delhi High Court on March 21,
2024, in OMP(COMM) 20/2024, due to conflicting views expressed by two Division
Bench judgments of the same court. The first judgment, Oil and Natural Gas
Corporation Ltd. v. Joint Venture of Sai Rama Engineering Enterprises (Sree) &
Megha Engineering & Infrastructure Ltd. (Meil) (2023 SCC OnLine Del 63), held
that the non-filing of a Statement of Truth is a procedural defect that is
curable and does not render an application under Section 34 non-est. In
contrast, the second judgment, Oil and Natural Gas Corporation Ltd. v.
Planetcast Technologies Ltd. (2023 SCC OnLine Del 8490), concluded that the
absence of a Statement of Truth is a fatal defect, rendering the application
non-est and incapable of stopping the limitation period. Recognizing this
conflict, the Single Judge referred the matter to a larger bench for
authoritative clarification. The Full Bench, comprising Justices Rekha Palli,
Navin Chawla, and Saurabh Banerjee, was constituted to resolve this issue, with
the judgment delivered on February 7, 2025.
Legal Issue: The primary legal issue before the Full Bench was whether
the non-filing of a Statement of Truth, or a defect in its filing, such as
blanks or lack of attestation, renders an application under Section 34 of the
A&C Act non-est? This question is critical because a non-est filing does not
stop the limitation period under Section 34(3) of the A&C Act, potentially
barring the application if refiled beyond the prescribed period of three months
plus thirty days. The court also considered whether Order VI Rule 15A of the
CPC, which mandates a Statement of Truth for pleadings in commercial disputes,
applies to applications under Section 34 of the A&C Act, given that such
applications may not strictly qualify as "pleadings" under Order VI Rule 1 of
the CPC.
Discussion on Judgments: The parties cited several judgments to support
their arguments, which the Full Bench meticulously analyzed in the context of
the non-filing of the Statement of Truth. The petitioner in OMP(COMM) 20/2024
relied on Oil and Natural Gas Corporation Ltd. v. Joint Venture of Sai Rama
Engineering Enterprises (Sree) & Megha Engineering & Infrastructure Ltd. (Meil)
(2023 SCC OnLine Del 63), where the Division Bench held that the absence of a
Statement of Truth is a procedural defect, not rendering the application non-est.
The court emphasized that Section 34 of the A&C Act does not specify procedural
requirements beyond setting out grounds for challenge and including the arbitral
award, and thus, procedural omissions like the Statement of Truth are curable.
In contrast, the respondent relied on
Oil and Natural Gas Corporation Ltd. v.
Planetcast Technologies Ltd. (2023 SCC OnLine Del 8490), which took a
stricter view, holding that the absence of a Statement of Truth, as mandated
under Order VI Rule 15A of the CPC, renders the application non-est. The court
in Planetcast emphasized the mandatory nature of the Statement of Truth under
the CC Act, citing its role in ensuring the veracity of pleadings and preventing
frivolous filings.
The Full Bench also considered
Vidyawati Gupta v. Bhakti Hari Nayak
(2006) 2 SCC 777, where the Supreme Court held that the absence of an affidavit
under Order VI Rule 15(4) of the CPC in a civil suit does not render the plaint
non-est, as such procedural requirements are directory and curable. This
precedent was pivotal in shaping the court’s view that procedural defects do not
automatically invalidate a filing.
Other judgments cited included
Jay Polychem (India) Ltd. v. S.E. Investment
Ltd. (2018 SCC OnLine Del 8848) and Director-cum-Secretary, Department of
Social Welfare v. Saresh Security Services Pvt. Ltd. (2019 SCC OnLine Del
8503), both of which involved multiple defects, including the absence of
signatures, affidavits, and vakalatnamas, leading to a non-est finding due to
cumulative deficiencies. Similarly, Indira Gandhi National Open University v.
Sharat Das & Associates (P) Ltd. (2023 SCC OnLine Del 7915) and Three C
Universal Developers (P) Ltd. v. Horizon Crest India Real Estate & Ors. (2020
SCC OnLine Del 2798) involved applications with multiple defects, such as
missing signatures, vakalatnamas, and arbitral awards, reinforcing that non-est
findings were based on cumulative flaws rather than the sole absence of a
Statement of Truth.
The court also reviewed
Bajaj Electricals Ltd. v. E-One Infotech Pvt. Ltd.
(2023 SCC OnLine Del 5154) and KNR Constructions Ltd. v. BHEL (2023 SCC OnLine
Del 4910), where a Single Judge held that a Statement of Truth, along with other
requirements like signatures on each page, is mandatory for a proper filing.
However, the Full Bench disagreed with this strict interpretation, finding it
overly pedantic. In A V Industries v. Neo Neon Electrical (P) Ltd. (2023 SCC
OnLine Del 5397), the Division Bench’s finding that a plaint without a Statement
of Truth was non-est was distinguished, as it involved a complete failure to
file the Statement of Truth even later, unlike the curable defect scenario in
arbitration applications.
Reasoning and Analysis of the Judge: The Full Bench’s reasoning was
grounded in a balanced approach to procedural compliance and substantive
justice. The court first addressed the applicability of Order VI Rule 15A of the
CPC to Section 34 applications. The petitioner argued that Order VI Rule 15A
applies only to "pleadings" (plaint or written statement) as defined under Order
VI Rule 1 of the CPC, and thus, an application under Section 34, being distinct,
is exempt. The court rejected this argument, relying on Section 10 of the CC
Act, which vests jurisdiction in Commercial Divisions for arbitration matters
and applies the CPC’s procedural framework, including Order VI Rule 15A, to such
applications. The court reasoned that the CC Act’s intent to streamline
commercial disputes extends to arbitration applications, making the Statement of
Truth requirement applicable.
However, the court held that the non-filing or defective filing of a Statement
of Truth is a procedural defect, not a fundamental one that renders the
application non-est. Drawing from Vidyawati Gupta, the court emphasized that
procedural requirements under the CPC are directory, aimed at expediting justice
rather than obstructing it. The court distinguished cases like Planetcast, where
non-est findings were based on cumulative defects, such as missing signatures,
vakalatnamas, and arbitral awards, rather than the sole absence of a Statement
of Truth. The court clarified that a non-est filing requires a finding of mala
fide intent to stall limitation, such as filing a mere "bunch of papers" without
substantive content.
The court further noted that while the Statement of Truth is essential, its
absence or defects (e.g., blanks or lack of attestation) can be cured, and the
court must consider the totality of defects and the applicant’s intent when
determining whether a filing is non-est. This approach ensures that procedural
technicalities do not unduly deprive parties of their substantive right to
challenge an arbitral award under Section 34.
Final Decision: The Full Bench answered the reference in OMP(COMM) 20/2024
by holding that the non-filing of a Statement of Truth or a defect therein does
not, by itself, render an application under Section 34 of the A&C Act non-est.
However, if accompanied by other defects that collectively indicate a mala fide
intent to merely stop the limitation period without a genuine intention to
pursue the application, the court may declare the filing non-est. The matter was
directed to be listed before the Roster Bench on February 19, 2025, for further
proceedings.
Law Settled in This Case: The judgment settles the law that
the non-filing or defective filing of a Statement of Truth under Order VI Rule
15A of the CPC, as applicable to commercial disputes, does not automatically
render an application under Section 34 of the A&C Act non-est. The court must
assess the cumulative effect of all defects and the applicant’s intent. A
procedural defect like the absence of a Statement of Truth is curable, and the
court retains discretion to condone delays in rectifying such defects, provided
the initial filing is within the limitation period under Section 34(3) of the
A&C Act. This ruling balances the strict limitation regime of the A&C Act with
the need to preserve substantive rights, ensuring that procedural lapses do not
unduly bar legitimate challenges to arbitral awards.
Case Title: Pragati Construction Consultants Vs. Union of India : Date of
Order: February 7, 2025:Case Number: FAO(OS) (COMM) 70/2024 :Neutral Citation:
2025 :DHC:717-FB:Name of Court: High Court of Delhi at New Delhi:Name of Hon'ble
Judge: Justice Rekha Palli, Justice Navin Chawla, Justice Saurabh Banerjee
Disclaimer: The information shared here is intended to serve the public interest
by offering insights and perspectives. However, readers are advised to exercise
their own discretion when interpreting and applying this information. The
content herein is subjective and may contain errors in perception,
interpretation, and presentation.
Written By: Advocate Ajay Amitabh Suman, IP Adjutor - Patent and
Trademark Attorney
Email:
[email protected], Ph no: 9990389539
Comments